NOTE: I actually wrote this post a week ago but I’ve been too busy working and shooting to find someplace with interweb access so I could post it. Sorry for the delay!
————————
It’s only been 5 days since I met up with the Temple caravan in Reno but it feels like a lifetime ago. It was a tough trip for the die-hard crew who did the drive but everyone arrived on the playa safe and sound late Tuesday night (around 12:30am) and then proceeded to unload the trucks for the next 5 hours. Life on the Temple crew is glamorous indeed!
We got off to a slow start because Home Depot was 2 days late delivering our lumber and building supplies but the crew has been working their tails off to try to make up for lost time.
We hit our first big milestone last night–the central tower for the first floor was lifted into place. After all these months of plannirg, working and praying, we finally have something tangible to show for our efforts. Seeing this section of the first floor put together really drives home the massive scale of this project. When all is said and done, the Temple will be 53 feet tall–almost 20 feet taller than our last project and dramatically more complex.
We don’t have internet or cellphone access at the Temple build site so we’ve had almost no contact with our friends and family but rest assured we’re thinking of you and we’ll post updates on our progress whenever we can. Thanks to everyone who has helped us get to this point!